Buildings Civil engineering Project status: Completed

Sljeme cable car – stations and tower foundations, Zagreb

RC works on the stations, route foundations and landslide remediation · new Sljeme cable car

Project details

Location
Sljeme, Zagreb
Client
Zagrebački električni tramvaj (ZET)
Building
Sljeme cable car – stations and towers
Our works
Formwork, reinforcement and concrete works
Period
completed November 2020

About the project

Alpha Concretum Gradnja took part in building the new Sljeme cable car for the client Zagrebački električni tramvaj (ZET), the Zagreb public transport company. We completed our works in November 2020.

Route and landslide remediation

Along the cable car route we built the foundations and foundation slabs of the towers – formwork, ribbed reinforcement of 12 and 14 mm diameter and larger to the reinforcement drawings, and machine placing of concrete. As part of the landslide remediation, we built the capping beam and walls.

Stations

At the lower station we built the reinforced concrete structure of levels -2 and -1: columns, beams, staircase and lift walls, floor slabs and inclined ramp slabs, with formwork up to 3.6 m high. At the Brestovac intermediate station we built the basement foundation and floor slabs, walls, columns, beams and the external staircase, and at the upper station the walls, columns, staircases and floor slabs.

What we built

  • Foundations and foundation slabs of the route towers
  • Landslide remediation – capping beam and walls
  • Lower station – RC structure of levels -2 and -1
  • Brestovac intermediate station – RC basement structure
  • Upper station – RC walls, columns, slabs and staircases
  • Formwork for walls, staircases, lift shafts, columns and beams
  • Ribbed reinforcement to reinforcement drawings
  • Machine placing of concrete

Site photos

Izvedba · 2020.

Looking for a reliable reinforced concrete contractor?

Get in touch – we will gladly review your project.

Send us your project