Civil engineering Project status: Completed

Karlovac expressway – Sajevac, Jelaši and Slunjska brda viaducts

RC works on the viaducts · Mostanje – Vukmanički Cerovac section

Project details

Location
Karlovac, Mostanje – Vukmanički Cerovac section (km 1+700 – 7+876.50)
Client
Hrvatske ceste d.o.o. (Croatian Roads)
Building
Expressway – Sajevac, Jelaši and Slunjska brda viaducts
Our works
Reinforcement, formwork and concreting; falsework
Period
started 27 January 2021

About the project

Alpha Concretum Gradnja took part in building the expressway through Karlovac on the route towards Split, on the Mostanje – Vukmanički Cerovac section (km 1+700 to km 7+876.50). The client was Hrvatske ceste d.o.o. (Croatian Roads), and we started work on 27 January 2021.

Viaducts

On the Sajevac, Jelaši and Slunjska brda viaducts we carried out the reinforcement, formwork and concreting of the column pad footings and the deck structure. For the same viaducts we also built the load-bearing falsework, including ground preparation.

Route drainage

Along the route we also carried out the reinforcement, formwork and concreting of separators and sand filters.

What we built

  • Reinforcement, formwork and concreting of column pad footings
  • Deck structure of the Sajevac, Jelaši and Slunjska brda viaducts
  • Load-bearing falsework including ground preparation
  • Reinforcement, formwork and concreting of separators
  • Sand filters along the route